2022 URD – SE Byers Avenue & SE 4th Street Reconstruction Project

Project ID: 
2022 URD Streets Project
Project Type:
Street
Project Status: 
Completed

What work is being performed?

  • Curb and gutter will be removed and replaced, as needed, to address drainage issues.
  • Sidewalks will be removed and replaced, as needed, to install the new curb and gutter, to address safety issues, and to ensure compliance with ADA standards.
  • ADA ramps will be installed to meet Federal ADA standards.
  • Catch basins and storm water pipe will be installed to improve and address drainage issues.
  • Roadway will be completely reconstructed to address subgrade failure.