Clone of Regarding the upcoming US30: Signal Upgrade (Pendleton) Project.

Regarding the upcoming US30: Signal Upgrade (Pendleton) Project.

Work in downtown Pendleton is scheduled to begin the week of February 7th and continue through April. Most of the work will be done Monday through Friday between 7:00 am and 5:00 pm.  We will be at the intersection of U.S. 30/SE Court Avenue and SE 1st Street to upgrade traffic signals and ADA curb ramps.

Crews will also be removing traffic and pedestrian signals at the intersections along Dorian Avenue at SE 1st Street and SW 4th Streets.

 

Upcoming Work

 

Later this week the contractor will start to move in construction equipment and set up traffic control.  Starting next week, traffic on U.S. 30/SE Court Avenue will be reduced to one lane.  Crews will also start the removal of existing signals and sidewalks.